MDOT Contracts Advertised for a July 26, 2011 letting.
Click Call # to Email a Question
CallDescriptionProposalEBSx FileAddendaEBSx AmendFuel PricesBid ListCadd FilesPlan IndexPermit DocBid Tabulations
01 Widen and Overlay approximately 12 miles of US 72 from beginning of 4-lane to Benton County line, known as Federal Aid Project No. NH-0007-01(076) / 106159301, in Marshall County.
Project Completion: 06/08/2012
1
1
02 Mill and Overlay approximately 13 miles of SR 15 from Newton County Line to beginning of 4-Lane at Philadelphia, known as Federal Aid Project No. STP-0022-02(051) / 106207301, in Neshoba County.
Project Completion: 11/18/2011
1
Fax1
1
03 Installing a traffic signal on SR 67 at Lickskillet Rd., known as Federal Aid Project No. HSIP-0064-01(028) / 105961301, in Harrison County.
Project Completion: 02/28/2012
1
1
04 Mill and Overlay approximately 10 miles of US 278 / SR 6 in Busbyville East of Denmark Road to the Pontotoc County Line, known as Federal Aid Project No. NH-0070-04(016) / 106160301, in Lafayette County.
Project Completion: 06/29/2012
1
Fax1
1
05 Mill and Overlay approximately 5 miles of US 11 from the Lamar County Line to Lincoln Road, known as Federal Aid Project No. STP-2170-00(023) / 106222301, in Forrest County.
Project Completion: 11/30/2011
Fax1
06 Mill and Overlay approximately 2 miles of US 161 from centerline of US 61 to the Sunflower River bridge, known as Federal Aid Project No. STP-9324-00(001) / 106200301, in Coahoma County.
Project Completion: 11/11/2011
07 Withdrawn
Construction of a Shop Building for the Materials Laboratory in Jackson, known as State Project Nos. BWO-9718-25(001) / 502350301 & LWO-9023-25(002) / 502350302, in Hinds County.
Project Completion: 01/31/2013